We build from start to tasteful finishing, we can handle from scratch from architectural drawing to setting out and then building to finish . And if you have you plan already, Share it with us we tell you the quantity of Materials needed then we get to your site and build from scratch to finishing.
3BED bungalows will take 2weeks for blocks works if all materials is available, same at 4Bed
Duplex takes 3weeks for blocks works then 2weeks for form work . A day for slab casting and another 3weeks for blocks work.