1. Excavation of the trenches for foundation or total area to depth of 2m Incase of unsuitable soil.
2. leveling and compaction of the excavated surface area with road base (rubbles),
3. Soil test to ascertain soil suitability
4. Setting out of pad footing positioning as contained in the structural drawings using profiles and lines,
5. Placement of reinforcement and neck column in the footing formwork
6. Concreting of pad footing and neck column, 7. Laying of solid block in the foundation,
8. Making of tie beam on the solid block wall, sand back filling in the whole surface area, leveling and compaction
9. Mechanically, making of solid ground floor of 10cm thickness,
10. Making of columns, beams and stair in the ground floor leading to first floor,
11. Construction of slab to structural design specification, same process is repeated for first floor to the flat roof
14. Pastering and rendering, painting,
15. Aluminum work for doors and windows,